|
microFIT (10kW and less):
All microFIT applications made to the OPA dated December 8, 2010 or later shall be screened to ensure capacity exists (see below).
For microFIT applications received prior to December 8, 2010, the process Step's 1 through 3 are revised as such:
- The applicant submits the Connection Review Application (Appendix 2) and Generator Connection Assessment Review (Appendix 3) forms and related information (equipment specifications and certifications, site plan drawing, and SLD).
- HHH and the applicant meet to discuss the project.
- HHH develops a Connection Cost Estimate.
- HHH provides the Connection Cost Agreement, Offer to Connect, and a Connection Agreement to the applicant.
- Applicant signs and returns Connection Cost Agreement.
- HHH performs work required on our part to accommodate the connection (where required). Applicant installs their generation and related equipment*.
- Applicant contacts HHH to inspect the installed meter base type and location, and location of the isolating switch.
- Applicant receives ESA Connection Authorization and forwards a copy of it along with their signed Connection Agreement to HHH.
- Once HHH is satisfied all requirements are met, HHH and applicant will set a date for connection.
- Connection is made. HHH updates internal files and notifies OPA of connection.
For microFIT applications received post December 8, 2010, the process Step's 1 through 3 are revised as such:
- The applicant completes and submits the Connection Review Application form (Appendix 2) to apply for capacity.
- HHH reviews the Connection Review Application form submitted by the applicant. Within 15/ 30 business days (defined by the OEB DSC), HHH will provide the applicant with an Offer to Connect or reason for refusal of connection request.
- Where HHH has made an Offer to Connect, the applicant shall complete and submit a Generator Connection Assessment Review form (Appendix 3) and related information (equipment specifications and certifications, site plan drawing, and SLD).
- Back to step 4 above, microFIT
|
|
FIT (greater than 10kW but not greater than 10MW):
- The applicant submits the Connection Review Application form
(Appendix 2).
- HHH completes the "Generator Pre-FIT Request for Information" form and returns to applicant for their OPA application.
- Applicant applies to OPA. Once OPA issues contract to applicant once TAT and DAT have been passed.
- The applicant contacts HHH.
- HHH requests Generator Connection Assessment Review (Appendix 4) forms and related information (equipment specifications and certifications, site plan drawing, and SLD). Submitted information must be signed and sealed by a Professional Engineer.
- HHH and the applicant meet to discuss the project.
- HHH/ applicant enter into a study agreement.
- HHH performs a Connection Impact Assessment (CIA) and if required involves any upstream LDC's who may need to do a CIA. Impact assessments may take up to 60-90 business days to complete depending on the circumstances as regulated by the OEB.
- HHH develops a Connection Cost Estimate.
- HHH provides CIA along with Connection Cost Agreement, Offer to Connect, and a Connection Agreement to the applicant.
- Applicant signs and returns Connection Cost Agreement
- HHH performs work required on our part to accommodate the connection. Applicant installs their generation and related equipment*.
- Applicant performs commissioning tests per CSA C22.3 No. 9-08, IEEE 1547, and completes HHH's "Commissioning and Equipment Verification Report" and provides the report along with any of their own commissioning tests to HHH.
- Applicant receives ESA Connection Authorization and forwards a copy of it along with their signed Connection Agreement to HHH.
- Once HHH is satisfied all requirements are met, HHH and applicant will set a date for connection.
- Connection is made. HHH updates internal files and notifies OPA of connection.
|